Rebuild a Pile Plan
Use the Rebuild Pile Plan command to update a pile plan after it has been changed in the field (e.g., you have deleted piles, such as a spliced pile) or if you imported as-built pile results prior to importing a pile plan.
Prerequisites:
- Licensed module; See the Subscription Plans page. For a license matrix by command, see the License page in the TBC Community. Also see View and manage licensed features.
- Imported as-built piling results
To access the command:
- Right-click a pile plan in the Project Explorer and select Rebuild Pile Plan.
Scenarios:
- If you import an as-built piling results file without having its associated pile plan in your project, the piles will appear only as vectors/lines, because the results file does not know the cross-section types that were used. If you then create a pile with the same name as an imported, as-built pile, and rebuild the plan, the as-built pile is updated with its cross-sectional shape.
Dependencies:
- None