Transfer Corridor Mass Haul Data to TILOS
The goal of this TILOS workflow is to guide you through the process of transferring data from a balanced corridor mass haul to TILOS scheduling software (version 8.0 or later).
Prerequisites:
- TILOS software installed on your computer
- Prior to importing corridor mass haul data into TILOS for the first time navigate to the Tours and Tutorials page on TCC. In the Training Videos, Tutorials and Data Sets section open Corridor Mass Haul > Data-TILOS files. Copy these files to the TILOS template directory:
- Trimble Mass Haul.hst
- Trimble Mass Haul (feet).hst
Steps |
Commands |
Notes |
||
1. |
Create a project with a balanced corridor mass haul. |
|
Return to this workflow when you are finished with the Corridor Mass Haul Workflow. Only the materials balanced will be exported to TILOS. |
|
2. |
Use the TILOS Mass Maul exporter to export the corridor mass haul balances as an (.xml) file.
|
|
In the Settings group, enter the size that you want the mass areas for earthworks sites to appear in TILOS. An entry of 30 will create a mass area 30m long on the distance axis in the TILOS mass haul diagram. Cut and fill mass areas get their size from the cut range and the fill range for the balance. |
|
3. |
Run the TILOS software. |
|
|
|
4. |
In TILOS, create a new project.
|
|
|
The TILOS Mass Haul XML exporter outputs values in project units. When a TILOS project is created select:
|
5. |
In TILOS, in the Settings for New Project dialog enter the project settings. Click Apply. |
|
|
Make sure you enter appropriate start and end distances for the data you are importing. |
6. |
In TILOS, save the new project. Enter the file name and click Save. |
|
|
|
7. |
In TILOS, import the TILOS (.xml) file created in step 2.
|
|
|
A profile file defines how data in the TILOS (.xml) file is imported. Business Center includes the profile information in the exported xml file. The following graphs appear:
|
8. |
In TILOS, schedule mass haul balances.
|
|
|
Cut and Fill tasks can be created after haulage types have cut and fill task templates specified. To update the settings for the Tasks graph, in the menu select Tools>options>Project (2) and update settings in the Mass Haulage settings. |